References may be made to IS 7215 for general guidance.
G-8.1 Access to Contractor's Works
The contractor should offer facilities for the inspection of the work at all stages.
G-8.2 Inspection of Fabrication
Unless otherwise, agreed, the inspection should be carried out at the place of fabrication. The contractor should be responsible for the accuracy of the work and for any error, which may be subsequently discovered.
G-8.3 Inspection on Site
To facilitate inspection, the contractor should during all working hours, have a foreman or properly accredited charge hand available on the site, together with a complete set of contract drawings and any further drawings and instructions which may have been issued from time to time.