1.9.1
Demolition and shoring of any part of an existing structure are not within the scope of work that is provided by either the fabricator or the erector. Such demolition and shoring shall be performed in a timely manner so as not to interfere with or delay the work of the fabricator or the erector.
1.9.2
Protection of an existing structure and its contents and equipment, so as to prevent damage from normal erection processes, is not within the scope of work that is provided by either the fabricator or the erector. Such protection shall be performed in a timely manner so as not to interfere with or delay the work of the fabricator or the erector.
1.9.3
Surveying or field dimensioning of an existing structure is not within the scope of work that is provided by either the fabricator or the erector. Such surveying or field dimensioning, which is necessary for the completion of the approval documents and fabrication, shall be performed and furnished to the fabricator in a timely manner so as not to interfere with or delay the work of the fabricator or the erector.
1.9.4
Abatement or removal of hazardous materials is not within the scope of work that is provided by either the fabricator or the erector. Such abatement or removal shall be performed in a timely manner so as not to interfere with or delay the work of the fabricator or the erector.